IKEA warehouses

STRENGTHENING OF FOUNDATION SOILS
Category
Floor slabs at logistics centres
Object
Regional warehouse LLC " IKEA MOS»
Focus
Re-leveling floors and improving the soils
Location
Moscow region
Time of work
2017 г.
The timing
40 days
TECHNOLOGY
DEEP INJECTION & SLAB LIFTING

Description:

In April 2017, work was carried out to strengthen the foundation soil using URETEK DEEP INJECTION. The concrete floors were lifted up to 8 cm at maximum by SLAB LIFTING injection.

The area of the work area is 10,000 m2. Work on strengthening the foundation soil and lifting the floor slabs was carried out during 40 days without stopping the logistics processes at the warehouse.

If you have not found an object or a situation similar to yours in the portfolio on the website, then order a specialist to select a project to analyze the pros and cons of technologies from the extensive database of completed Uretek projects.
Back to projects
Standard projects and cost
Leave a comment
Comments
Thank you for your comment!
Close

Leave your phone number and our consultant will contact you

Choose a convenient time to call

Leave your email and we will send you this article

  • Services
  • Uretek methods
  • Projects
  • Video
  • About us
  • Contacts
  • Moscow
    +7 495 268 01 47
    St. Petersburg
    +7 812 627 15 05
    Rostov on Don
    +7 863 308 17 98
    Kazan
    +7 843 206 03 64
    Nizhny Novgorod
    +7 831 429 17 68
    Sevastopol
    +7 869 222 31 91
    Novosibirsk
    +7 383 280 42 61
    Uretek